Step 1
Site Preparation & Setting Out
Site is cleared and levelled. Setting out confirms exact position, levels, and orientation of the A-frame structure.
Build Process
A clear 4-phase journey with 14 execution steps from groundworks to final handover.
Phase 1
Groundworks
Steps 1-2: setting out and foundations.
Phase 2
Structure
Steps 3-9: frame, envelope, and openings.
Phase 3
Services
Steps 10-11: plumbing and electrical works.
Phase 4
Finishes & Handover
Steps 12-14: finishes, QA, and handover.
Step 1
Site is cleared and levelled. Setting out confirms exact position, levels, and orientation of the A-frame structure.
Step 2
Excavation, hardcore compaction, anti-termite treatment, damp proof membrane, reinforcement, concrete footings/slab, and anchor bolt positioning.
Step 3
Structural members are fabricated, erected, aligned, bolted, welded, primed, and protected against rust.
Step 4
Steel floor joists or slab construction is completed, then insulation, screed, and floor finishes are installed.
Step 5
Steel purlins and battens are fixed; roofing sheets, membranes, insulation, and wall cladding are installed.
Step 6
Flashings, ridge caps, fascias, barge boards, gutters, and downpipes are installed.
Step 7
Insulation materials are installed in roof and wall cavities for comfort and energy efficiency.
Step 8
Light gauge studs, gypsum/cement boards, and rhino ceiling boards with insulation/access panels are installed.
Step 9
Aluminium windows/doors, glazing, and hardware are installed; openings are sealed for weather tightness.
Step 10
Water supply and drainage pipework is installed/tested; sanitary fittings, kitchen plumbing, and water heating are fixed.
Step 11
Conduits and wiring are installed; boards, switches, sockets, and lighting points are completed to safety standards.
Step 12
Wall/floor tiling, plastering or skimming, and kitchen cabinets/joinery are completed.
Step 13
Internal/external priming and painting are completed; final fixtures, fittings, and lighting are installed.
Step 14
Full inspection, service testing, defect rectification, cleaning, and client handover.
Quick answers to the most common planning questions.
Cavara Cabins specializes in the design and construction of modern steel-framed A-frame cabins for lodges, private retreats, Airbnb investments, and resort developments.
A standard 30 to 45 square metre cabin typically takes 6 to 8 weeks, while a 45 to 65 square metre cabin usually takes 8 to 12 weeks, subject to scope and site conditions.
Yes. Cavara provides the architectural and structural drawings needed for approvals, and assistance with council submissions can be arranged.